ILF is awarded contracts for the Ernsthofen and Lienz substations
moreFor the first time, ILF Consulting Engineers was commissioned by Austrian Power Grid AG (APG) to perform design services for high-voltage installations.
Basically, the services to be provided for the Ernsthofen substation involve replacing and relocating transformers and constructing a new control building incl. 10 kV switchgear.
The services for the Lienz substation include upgrading the 380/220 kV switching station and installing a 380/220 kV RHU43 transformer bank incl. corresponding 380/220 and 30 kV feeders.
The services comprise status-quo documentation, review of structural and soil conditions, preparation of tender documents and detailed design for all necessary upgrade measures and parts of the permit application design