Refinery turnaround successfully completed
moreILF has built up vast experience in the refinery business over the last decades. Trusting in our capabilities, one of ILF’s major clients asked our engineers to assist them with a turnaround in their refinery in Romania.
The maintenance work for this turnaround had to be completed within one month. While three projects only had to be completed, one of the projects had to be completely implemented within this short period of time. The ILF team completed more than 30 tie-ins for the ongoing tank construction projects during this month.
During the turnaround, ILF’s team of engineers was involved in all activities related to:
- piping, mechanical, civil, electrical and instrumentation engineering
- safety coordination
- logistics
We are very proud to say that in the more than 3,000 hours of supervision and technical assistance provided by ILF, not a single incident occurred.