ILF continues advisory to Red Sea Global
moreRed Sea Global, the developer of the world’s most ambitious regenerative tourism destinations, has appointed ILF as an Independent Engineer for the implementation phase of the primary utility system currently being developed by a consortium led by ACWA Power.
The project includes the provision of renewable power, potable water, wastewater treatment, district cooling and solid waste treatment for 16 hotels, an international airport, and infrastructure that will form Phase One of The Red Sea destination in Saudi Arabia.
Key Facts:
- Solar PV: 340 MWac
- BESS: 1,200 MWh
- Internal Combustion Engine: 108.98 MW
- SWRO: 32,500 m3/day
- Wastewater: 18,300 m3/day
- District Cooling: 32,500 RT
- Solid Waste Management: 11,775 T/year
ILF already acted as a technical advisor during the tendering stage of the PPP project, which resulted in a Utilities Concession Agreement (UCA) worth roughly USD 1.5 billion.
The extension of ILF’s involvement in this landmark development is seen as both an expression of confidence as well as a confirmation of the call for ILF to continue to deliver Engineering Excellence with ILF’s integrated team from its offices in Saudi Arabia, Austria, Germany and Poland.